New Wismar-Mackenzie Bridge 97% complete

Reading Time: 2 minutes

The Ministry of Public Works on Monday said that physical works on the New Wismar-Mackenzie Bridge in Linden, Region Ten, are now 97 per cent complete.

This update was provided to the Minister of Public Works, Juan Edghill, on Friday, during a targeted assessment visit to the project site.

The Minister held a multi-stakeholder meeting which included technical staff from the Ministry, contractors China Railway Construction (Caribbean) Company Ltd. and GuyCo Construction Inc., and the consultancy firm, Politecnica.

During the visit, Minister Edghill and representatives from various stakeholders conducted an on-site walkthrough of the 233-metre-long concrete bridge, where concrete placement is currently at 97 per cent.

The walkthrough also included an inspection of the secondary connections leading to and from the bridge.

A project debrief revealed that works on the Western End (Wismar side), specifically the West Watooka Connector and Dacoura Haul Roads, are 33 per cent complete.

For these two main arteries, subgrade preparation, subbase, crusher-run base, and curbing are 100 per cent complete.

The foundation works for the roundabout are also 100 per cent complete, with curbing at 50 per cent. Additionally, work on the Burnham Drive approach is advancing, with subsurface works at 38 per cent, curbing at 39 per cent, and culvert works currently underway.

Meanwhile, the Eastern End of the bridge is 27 per cent complete, accounting for foundation and retaining structures. At the time of the visit, 3,750 prefabricated vertical drains had been installed and geotextiles laid, with the contractor currently placing white sand and crushed stone as part of the subsurface works.

A new culvert at the Washer Pond Road approach at Noitgedacht has been successfully installed, and construction is underway for the retaining wall of the main embankment. Excavation and geotextile installation are complete, with backfilling ongoing to prepare for final surfacing.

The project remains on track to be fully operational by June 2026, pending the completion of the connector roads. When finished, the toll-free crossing will feature two barrier-separated pedestrian walkways, modern lighting, and two new roundabouts on both the eastern and western sides of the bridge.

The Ministry of Public Works said it remains committed to delivering high-quality infrastructure that meets the growing demands of Region Ten and the wider country.

The Ministry thanked the residents of Linden and commuters for their continued cooperation and patience as we execute these transformative works.

Leave a Reply

Your email address will not be published. Required fields are marked *

Discover more from Guyana News Pulse

Subscribe now to keep reading and get access to the full archive.

Continue reading